Digesters.

Engineering Solutions for Dairy Digesters

4Creeks is at the forefront of providing engineering consulting services for an exciting opportunity available to dairies in California. We work with Dairymen to understand their needs and conduct feasibility analysis to ensure a digester is a good investment opportunity. If your dairy will benefit from a digester we offer start to finish assistance, beginning with conceptual site plans, assistance with grant preparation, and we specialize in permitting. We work closely with the Water Board, Air District, and Counties to ensure the permitting process goes smoothly. Throughout our design process, we work with the client to ensure dairy operations benefit from the design of the digester, and that it works seamlessly with current and future dairy management. Upon completion of construction drawings and specifications, we assist the client with bidding and construction management.

Our Process & Services

digester-process

Permitting Services

County Permits include:

  • CEQA compliance / permit updates
  • Construction documents for building permits
  • Encroachment permits

Water Board Permits include:

  • Waste Management Plan updates
  • Pond Workplan
  • CEQA plan and inspections
  • Post Construction Pond Report

Air District Permits include:

  • Assist with site plans
  • Applications for Authority to Construct

Recent Digester Project Experience:

We are proud to have contributed our expertise on the projects found below. We have participated in many of the covered-lagoon digesters currently in operation or under construction in California to date. This is a major achievement that we are excited to be involved in. We are contributing to the pioneering of a new industry and are thankful for the opportunities we’ve had to assist these valuable clients in long term sustainability for dairies.

Carlos Echeverria & Sons Dairy Digester

Project Status: Under Construction

Recipient of funding from the California Department of Food and Agriculture (CDFA) and the California Energy Commission (CEC), this double-lined, covered lagoon digester will produce 1 MW of electricity. Waste engine heat will be used to cool milk and produce hot water.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

West Star Dairy Digester

Project Status: Under Construction

Recipient of funding from CDFA and CEC, this two cell, double-lined, covered lagoon digester will produce 1 MW of electricity. It is set up to add engine capacity to deliver stored energy. It is also a potential location for co-digestion.

  • Permitting
  • Pond Design
  • Site Design\
  • Project Management

Development Team:

Lakeview Farms Digester

Project Status: Under Construction

Recipient of funding from CDFA and CEC, this double-lined, covered lagoon digester will produce 1 MW of electricity. It is also one of the anchor dairies in the Kern Cluster, with the goal to produce vehicle fuel as well as electricity.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

Old River Dairy Digester

Project Status: Completed

The Old River Dairy Digest project is a 2 MW, two cell, double-lined lagoon digester and is the largest in the state.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

Verwey Farms – Hanford Digester

Project Status: Completed

4Creeks assisted the client with Anaerobic Digester design from concept to project completion and assistance with Construction Management.  The facility is a 1 MW covered lagoon manure only dairy digester.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

Verwey Farms – Madera Digester

Project Status: Completed

4Creeks assisted the client with Anaerobic Digester design from concept to project completion and assistance with Construction Management.  The facility is a 1 MW covered lagoon manure only dairy digester.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

Pacific Rim Dairy Digester

Project Status: Completed

4Creeks assisted the client with Aenerobic Digester design from concept to project completion and assistance with Construction Management.  The facility is a 1 MW covered lagoon manure only dairy digester.

  • Permitting
  • Pond Design
  • Site Design
  • Project Management

Development Team:

Open Sky Dairy Digester

Project Status: Completed

4Creeks analyzed the existing dormant digester at the project site. We  coordinated with Water Board for re-approval of digester and continued operations and maintenance for digester system.

  • Permitting
  • Digester Analysis

Development Team:

GJ Te Velde Dairy Digester

Project Status: Completed

4Creeks prepared and submitted County permits for planning approval, assisted with building permits, updated Water Board Waste Management Plan to be consistent with digester operations.

  • Permitting
  • Digester Analysis

Development Team:

Grant Applications

Assisted in submittal of over a dozen 2017 CDFA Grant Applications

Our trusted partner can build your Digester

4Creeks has teamed with various experts in the digester funding, management, and construction fields and we are glad to help answer the questions you might have in your decision process.  If we can’t answer questions specifically, we know someone who can and will connect you to the right people.

Most Recent Projects